Match the outputs defined in column 2, with the process named in column 1, inserting your answer (selection from column 1) in the space provided in column 3.

Process

Outputs

Answer

(number)

1. Identify Stakeholders

A. Issue Log, Change Requests, updates to the Project Management Plan, Project documents and OPAs

3

2. Plan Stakeholder Management

B. Stakeholder Register

1

3. Manage Stakeholder Engagement

C. Work Performance Information, Change Requests, updates to the Project Management Plan, Project documents and OPAs

4

4.Control Stakeholder Engagement

D. Stakeholder Management Plan, Project document updates

2


Match the process explanations defined in column 2, with the process named in column 1, inserting your answer in the space provided in column 3.

Process

Process Explanation

Answer

(number)

1. Identify Stakeholders

A. Actions taken to monitor overall project stakeholder relationships, reviewing and amending strategies and plans to improve levels of stakeholder engagement

4

2. Plan Stakeholder Management

B. Using a variety of interpersonal and management skills and communication methods, the actions taken to communicate and work with stakeholders to develop their level of engagement in the project

3

3. Manage Stakeholder Engagement

C. Actions taken to identify people, groups or organisations that could impact, or be impacted, by a decision, activity, or outcome of the project.

1

4.Control Stakeholder Engagement

D. Actions taken to develop strategies to effectively engage stakeholders throughout the project, based on their identified needs, interests, influence, impact and importance.

2

DISCLAIMER

Firebrand Training grants you a personal, non-exclusive, non-transferable license to access and use the site. You may download or print material from the site only for your own personal, non-commercial use. Read our full terms and conditions on https://firebrand.training/uk/learn/terms-and-conditions.