1. Match the outputs defined in column 2, with the process named in column 1, inserting your answer in the space provided in column 3.
Process |
Outputs |
Answer (number) |
1. Plan Communications Management |
A. A. Work performance information / Change requests / Project management plan updates / Project document updates / Organisational process assets updates |
|
2. Manage Communications |
B. Communications Management Plan / Project Document Updates |
|
3 Control Communications |
C. Project Communications / PM Plan updates / project document updates / Organizational Process Asset Updates |
2. Match the process explanations defined in column 2, with the process named in column 1, inserting your answer in the space provided in column 3.
Process |
Process Explanation |
Answer (number) |
1. Plan Communications Management |
A. Creating, collecting, distributing, storing and retrieving project information as stated in the communications management plan |
|
2. Manage Communications |
B. Developing an appropriate approach and plan for project communications based on the information the needs and requirements of different stakeholders |
|
3. Control Communications |
C. Monitoring and controlling communications within the entire project lifecycle to meet stakeholders’ information needs. |
Firebrand Training grants you a personal, non-exclusive, non-transferable license to access and use the site. You may download or print material from the site only for your own personal, non-commercial use. Read our full terms and conditions on https://firebrand.training/dk/learn/terms-and-conditions.