"The process of estimating the type and quantities of material, human resources, equipment or supplies required to perform each activity."
The definition shown above in italics is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute Inc., 2013
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute Inc., 2013 Figure 6-12 Page 161
Estimating the type and quantities of material, people, equipment or supplies required to perform each activity.
Resources include:
Example: Resources for a seminar project
Leads to Estimate Activity Durations (6.5) and Estimate Costs (7.2)
Suggested steps:
Example: An events organizer using the bottom-up estimating technique, basing it on a detailed WBS for a large corporate event.
Activity Resource Requirements
Resource Breakdown Structure
Project Document Updates
Firebrand Training grants you a personal, non-exclusive, non-transferable license to access and use the site. You may download or print material from the site only for your own personal, non-commercial use. Read our full terms and conditions on https://firebrand.training/dk/learn/terms-and-conditions.